Reorder point calculator: when to order again

Give it your daily usage, the supplier lead time and the safety stock you hold. It returns the stock level at which you should place the next order.

Reorder point equals daily usage times lead time in days, plus safety stock. At the default numbers you reorder when 680 units are left.

Written by Procurement VMS Editorial Team · Reviewed by Michael, Procurement Advisor Expert · Updated

Go to the calculator

Your numbers

The boxes start with an example so you can see how it works. Replace them with your own figures.

Your result

Reorder point680units

Place the next order when stock drops to 680 units. By the time the order arrives you will have used about 560 units, which leaves your 120 units of safety stock untouched.

Demand during lead time560 units
Reorder point680 units
Days of stock at the reorder point17.0 days

The currency box changes the label only. Enter amounts in the currency you choose.

Free PDF and Excel

Save this result as a PDF guide and an Excel model

Free to download. You enter your name, work email and phone number, and the files are ready at once.

  • PDF guide with the formula, a worked example and a checklist of what to enter
  • Excel model with live formulas, so your own numbers recalculate at once
  • Ready at once after the form, with no account to create

The files open with the example numbers from the page. Type yours over the blue cells in the Excel file. The calculator on this page is free to use without a form.

How the reorder point calculator works

The formula

Reorder point = (average daily usage x lead time in days) + safety stock.

The reorder point turns a vague habit of ordering when stock looks low into a number. It is the stock level at which the order has to go out, so that the delivery lands before you run dry.

Lead time is the number people get wrong. Count from the day you decide to order, not the day the supplier confirms it. Approval time, supplier processing, transit and receiving all belong in it.

The example numbers are illustrative and are not benchmarks. Use your own data for any decision.

How to use it with your own data

  1. Measure daily usage over a normal stretch, and leave out one-off bulk orders that would inflate it.
  2. Use the lead time you actually see, such as the average of the last ten deliveries. The lead time calculator adds up the stages for you.
  3. Add safety stock from the safety stock calculator so the trigger covers late deliveries.

Mistakes that skew the answer

Using the promised lead time

The supplier quotes the best case. If the last ten deliveries averaged 17 days, calculate with 17, not 14.

Forgetting safety stock

Without it the trigger only works when everything runs on time, which is rare enough that stock-outs follow.

Setting it once and leaving it

Usage and lead time drift. Review the number each quarter or after any change in supplier or season.

What to do with the result

Load the reorder point into your inventory system or a simple min and max sheet, then pair it with the order size from the EOQ calculator. If you buy through a blanket order, use the figure to schedule releases in your blanket purchase order template.

Questions about the reorder point calculator

What is a reorder point?

It is the stock level that triggers a new purchase order, set so that the delivery arrives before stock runs out.

Is reorder point the same as safety stock?

No. Safety stock is the buffer inside the reorder point. The reorder point also covers the demand that happens while you wait for the delivery.

How often should I recalculate it?

Every quarter for stable items, and straight away when usage or supplier lead time changes.

What if lead time varies a lot?

Use the average for the lead time and raise safety stock to cover the swings. The safety stock calculator has a field for lead time variation.