CHANGE ORDER
1
NUMBER, DATE AND PROJECT
Change order CO-03
Date: 19 Oct 2026
Project: Office fit-out, Level 4
2
PARTIES AND CONTRACT
Contractor: Keystone Interiors Ltd
Customer: Harlow Foods Ltd
Contract: FO-2026-07, sum 140,000
3
DESCRIPTION OF CHANGE
Add six data points in meeting rooms 2 and 3
4
COST EFFECT
Add: 3,900.00
Revised contract sum: 143,900.00
5
TIME EFFECT
Add two working days
New completion: 14 Nov 2026
6
RUNNING LOG
CO-01: 4,200 · CO-02: 3,100 · CO-03: 3,900
Total changes: 11,200
7
APPROVAL
Customer: R. Ahmed, Facilities, 19 Oct 2026
Contractor: P. Cole, 19 Oct 2026

Sample for illustration. Company names, numbers, tax registrations and bank details are fictional.

Source: Change Order, decoded by Procurement VMS